Council Works Update
Council works and projects update as at 1 December 2024:
Sorell Streetscape – Works are nearing completion in Station Lane. Additional street trees and furniture to be installed shortly.
Sorell Carriage Shed – Lighting has arrived and will be installed shortly.
Gate Five Road/Carlton Beach Road (Vulnerable Road User Program) – Guard rail has been installed and footpath works will commence early/ mid-November.
South East Training and Jobs Hub – Under slab services have been installed. Concrete piers, edge beams and slab have been installed. Steelwork to commence early November.
BMX Track Lighting – The electrical conduit has been installed. Cages for the light tower footings have been ordered and should be installed by late November.
Penna Beach Gravel Track – Works have commenced on site.
Sorell Memorial Hall Extension – Floor plans have been finalised and development application has been submitted to Council.
Midway Point Footpath Renewals – Works are underway with Midway Street 50% complete.
Road Re-seal Program – The tender for works has closed, a contract will be awarded in due course.
Road Re-sheet Program – Works are due to commence in November across 10 sites. Woods & Burdon Road, Woolleys Road, Kellevie Road, Bream Creek Road, Marion Bay Road, Bay Road, Hillcrest Road and Heatherbell Road.
Erle Street Carlton River – Stormwater upgrade and pipeline re-alignment works are to commence Thursday 12 December 2024 and the reline on Thursday 19 December 2024.
Roadside Spraying – Councils annual roadside spraying program is due to commence in November 2024 weather permitting.
Footpath and Hard surface Spraying – Footpath and hard surface spraying, including pedestrian crossings and all traffic islands and round-bouts will commence mid-November.
Allambie Road Reconstruction – This project is currently out for tender.
Coastal & Estuarine Risk Mitigation Program (CERMP) – Design planning continues for the further 15 outfalls.