Council Works Update

Council works and projects update as at 1 December 2024:

Sorell Streetscape – Works are nearing completion in Station Lane. Additional street trees and furniture to be installed shortly.

Sorell Carriage Shed – Lighting has arrived and will be installed shortly.

Gate Five Road/Carlton Beach Road (Vulnerable Road User Program) – Guard rail has been installed and footpath works will commence early/ mid-November.

South East Training and Jobs Hub – Under slab services have been installed. Concrete piers, edge beams and slab have been installed. Steelwork to commence early November.

BMX Track Lighting – The electrical conduit has been installed. Cages for the light tower footings have been ordered and should be installed by late November.

Penna Beach Gravel Track – Works have commenced on site.

Sorell Memorial Hall Extension – Floor plans have been finalised and development application has been submitted to Council.

Midway Point Footpath Renewals – Works are underway with Midway Street 50% complete.

Road Re-seal Program – The tender for works has closed, a contract will be awarded in due course.

Road Re-sheet Program – Works are due to commence in November across 10 sites. Woods & Burdon Road, Woolleys Road, Kellevie Road, Bream Creek Road, Marion Bay Road, Bay Road, Hillcrest Road and Heatherbell Road.

Erle Street Carlton River – Stormwater upgrade and pipeline re-alignment works are to commence Thursday 12 December 2024 and the reline on Thursday 19 December 2024.

Roadside Spraying – Councils annual roadside spraying program is due to commence in November 2024 weather permitting.

Footpath and Hard surface Spraying Footpath and hard surface spraying, including pedestrian crossings and all traffic islands and round-bouts will commence mid-November.

Allambie Road Reconstruction – This project is currently out for tender.

Coastal & Estuarine Risk Mitigation Program (CERMP) – Design planning continues for the further 15 outfalls.